New Case Studies

Staines to Farnborough Data Centre Relocation

2000 devices relocated in multiple phases

  • 119 Racks of equipment
  • Full rack, cable & hardware audit
  • Installation of infrastructure cabling
  • Production of rack elevations, port maps & patching schedules
  • Pre-cabling of destination data racks plus application of laminated & engraved labels
  • Secure overnight & outside office hours relocations
  • Re-cabling & dressing of looms with 10mm Velcro
  • Onsite support during power-cycling process

Manchester & Ewloe to Chester Office Relocation

272 users relocated in 3 days

  • Site survey of all locations
  • Supply of IT crates and anti static bubble wrap bags
  • Decommissioning and packing of all items
  • TFT monitors mounted on arms
  • Identical setup on every desk to client specification
  • All cables reconnected, dressed & contained in spiral trunking
  • Logon and connectivity test of all user devices including IP phones

Reading to Frankfurt & Munich Server & SAN Relocation

22 servers, 4 SAN, 4 switches & 2 firewalls

  • Devices pre-labelled with destination city and rack position
  • Destination loads split into separate server cases
  • Load accompanied at all times while in transit
  • Secure overnight storage en route
  • Devices racked in Frankfurt & Munich to client specification
  • Client regularly updated during relocation
  • Project completed in 34 hours & client commissions devices 12 hours ahead of schedule