From London to New York, Paris & Dubai, Seraphine maternity stores can be found in all the top fashion capitals.

Winner of the Queen's Award for Enterprise in 2015, Seraphine’s fashionable maternity clothes offer a wide range of chic options for pregnancy, and their nursing clothes collection ensures that the style continues well after baby is born.

How we helped

Having secured stunning new offices in London’s Notting Hill, Seraphine approached Computer Relocations to help with the movement of their datacentre. The existing installation had grown organically over the past few years and had become increasingly difficult to manage. This is a common issue for IT managers who inherit datacentres and the relocation was recognised as an ideal opportunity to start afresh.

Pre-planning including site survey

Full cable and patch audit

Rack design and power Provision

Weekend relocation to reduce disruption

Cable looms made in advance

Entire relocation completed in 13 hours

180 patch connections and port audits, 20 devices and 5 CRL Engineers

Following an initial site survey, CRL introduced their rack and cable specialist. Having outlined the various options, it was decided that a full audit should be completed and the results of this would be used as a template not only for recabling, but also for ongoing management. Advice on rack design and power provision were also included in the discussions, and the decision was made to purchase all new patch and power cables plus PDUs.

Bright an early on a Saturday morning, CRL’s hardware relocation team arrived on site in the West End. Working in central London always presents challenges, however a thorough site survey allows us to put in place the personnel and equipment required to overcome the most difficult obstacles. The hardware was de-racked, secured in our rolling server cases and en route to the new site in less than three hours.

In the days preceding the move all the cables had been unpacked, straightened and grouped together. Looms had been created using 10mm Velcro and pre-printed Brady labels applied to all the cable ends. Whilst the hardware was being relocated, our cablers started to install the pre-made looms in preparation for its arrival.

Within two hours of its safe delivery to Holland Park, all the hardware had been re-racked as per the diagram created in conjunction with Seraphine. Once the installation had been inspected and approved the process of applying patch and power began.

Once patch and power had been applied, the cables were secured in the cable management strips. Great care was taken to ensure the labels were clearly visible. Obviously ensuring accurate connectivity was critical, however making the future management of the installation as easy as possible was also a priority. The re-cabling was completed around 22:00, just 13 hours after the relocation began and the improvement is clear to see.

Request a free site survey

Computer Relocations currently facilitated a move of our IT infrastructure from our old office to a new one on the same business park. From the initial quote, through advise on how best to label equipment and onto the whole moving process I cannot recommend them highly enough.

Not only did the move go very smoothly, they fixed some issues with our hardware that we were not aware of and left the new server room in a very tidy and organised manner. From the time we shut down our servers to when we were up and running and our business back to normal, was just 7 hours. 2 of those being our own IT team’s back-end work.

Overall superb and thanks again to the friendly and helpful team.

Head Of Acquisitions & Analytics

Koch Media